Regional Councillors to consider next steps for Westport flood protection
The West Coast Regional Council will consider the next steps for the Westport Flood Protection Scheme at its meeting on Tuesday 1 December 2026.
Public consultation on changes to the scheme ran from 21 September to 21 October 2026. A total of 83 submissions were received, with 82% supporting the Optimised Hybrid Scheme (Option Two).
The consultation feedback highlighted concerns about affordability and how costs should be shared. Other key topics included the level of flood protection, climate change, properties outside the scheme or adversely affected by it, confidence in the Council’s ability to deliver the work, the consultation process, insurance and wider community benefits such as walking and cycling trails.
Regional Councillors will be asked to note the recommendations of the Community Consultation Report, which summarises the consultation outcomes, and direct staff to progress them. The recommendations include:
reviewing the scheme rating system through the Long-Term Plan 2027–37
reviewing, jointly with Buller District Council, whether the Westport Rating District Joint Committee Terms of Reference and membership remain fit for purpose
continuing to pursue Crown and third-party funding
engaging with insurers and report verified information to the community
exploring value-add opportunities with community groups without delaying the programme
and confirming the Adaptation Fund eligibility policy as soon as possible.
Regional Councillors will also be asked to adopt an amended 2024–2034 Long-Term Plan, which sets out how the revised scheme would be funded and delivered. The Westport Flood Protection Scheme amendments are the only changes that have been made to the Long-Term Plan.
Agreement has now been reached in principle with government funders to extend the current Crown project funding to the end of 2029. Funding will be released based on agreed milestones and gateways. A variation to the Ministry for Cities, Environment, Regions and Transport (MCERT) Funding Agreement is being finalised.
Councillors will consider how the scheme will be delivered in stages, with decision points along the way and a cap on the amount ratepayers would be required to contribute.
They will also be shown the indicative construction schedule based on no more than three construction fronts at any one time, with close-out and defects liability continue to December 2030. The dates are indicative and depend on the Council decision, funding approval, consents and land access.
The first stage would be the start of construction of the Avery’s stopbank, followed closely by Floating Lagoon stopbank (consent pending). This would be followed by Carters Beach and Upper Buller from mid 2027, subject to consenting. Councillors will also consider authorising design work for future stages and approving a variation to the Crown funding agreement.
An update was provided to the Westport Rating District Joint Committee at its meeting this week.
-ENDS-
For further information please contact:
Amanda South,
Senior Communications Advisor
Notes to editors:
The Westport Flood Protection Scheme is being delivered by the West Coast Regional Council as part of the Resilient Westport programme of work.
Two options were consulted on under the Special Consultative Procedure.
Option One - Core protection scheme
The main Westport Flood Protection Scheme built to:
1.5% AEP (Annual Exceedance Probability) protection level
based on the current climate
400mm of freeboard (additional height to allow for uncertainties)
The revised alignment of the Carters Beach stopbank (built to a 1.5% AEP, plus 300mm freeboard).
Total additional scheme borrowing required is $22.5m, in addition to $10.2m already committed. Total borrowing up to $32.7m.
Option Two - Optimised hybrid scheme
The Optimised Hybrid Scheme provides an extension of Option One for the main Westport Flood Protection scheme, and Carters Beach.
1.5% AEP (Annual Exceedance Probability) protection level based on the current climate
400mm of freeboard
The revised alignment of the Carters Beach stopbank (built to a 1.5% AEP, plus 300mm freeboard).
The difference involves constructing some short sections of stopbank in a way that they can be raised more cost-effectively in the future if required.
Total additional scheme borrowing required is $23.6m, in addition to $10.2m already committed. Total borrowing up to $33.8m.
Both options provide a level of protection equivalent to a 1 in 67-year flood and would protect Westport from a flood comparable to the July 2021 event.