Westport Flood Protection Scheme
Reset
In 2026, a review of the Westport Flood Protection Scheme (WFPS) has been carried out, after it became clear that there were affordabilty issues.
The costs of the original scheme are now predicted to reach about $70 million, so the project team has worked on ways to reduce that and still deliver a more credible scheme.
One tool for doing so is to lower the level of protection to Westport to protect against an approximately 1 in 67-year flood (similar to July 2021) – as opposed to 1 in 100-year previously proposed. The level of freeboard (extra height allowance for uncertainty) would also be reduced from 600mm to 400mm following enhanced computer modelling.
The project reset has financial implications for ratepayers and represents additional debt for West Coast Regional Council (WCRC).
These proposed changes represent a significant variation from what is included in the West Coast Regional Council’s current Long-Term Plan (2024-2034) and what was consulted on with the community in 2021. Therefore, additional consultation is required using a Special Consultative Procedure.
Special Consultative Procedure
A Special Consultative Procedure (SCP) is a highly structured, formal public consultation process governed by the New Zealand Local Government Act 2002.
On 25 August 2026, Regional Councillors approved Council undertaking a Special Consultative Procedure on proposed scheme changes and voted to approve the next set of actions to progress the reset of the scheme.
The Special Consultative Procedure will ask the community to consider two options (below). Another option was considered but deemed too costly.
Option One is the main Westport Flood Protection Scheme (the Core Protection Scheme) built to a 1.5% AEP (Annual Exceedance Probability) protection level, based on the current climate, with 400mm of freeboard (extra contingency height). Plus, the revised alignment of the Carters Beach stopbank built to a 1.5% AEP, and 300mm of freeboard. This level of protection would protect Westport from a comparable flood to the July 2021 event but does not allow for future climate change.
Option Two is an Optimised Hybrid Scheme that builds on Option One for Westport and Carters Beach. It is designed for current climate conditions, with allowance to raise the height of the floodbanks in the future. The additional cost is estimated at about $1 million. The difference is that at select constrained locations, short sections of stopbank would be constructed with a wider footprint that can be cost-effectively built on in the future. For now, they would be built to the same height as Option One and offer the same level of flood protection.
Dates for the consultation will be advertised once finalised. The next step is for the WCRC to consider and approve the consultation at its 1 September 2026 meeting.
Cost implications
The tables below indicate the costings and rating implications of the proposed options:
Option One
Option Two
What is the plan for Carters Beach and Snodgrass Road?
It is still the intention to deliver flood protection for these communities.
Flood protection at these locations was not funded by central government, despite Carters Beach being including in the Kawatiri Business Case request for co-funding.
This Special Consultative Procedure includes funding for Carters Beach, as it has interdependencies with the main scheme and must be delivered alongside it.
The flood modelling shows that building the Westport stopbanks will change how water moves in the Lower Buller, affecting Carters Beach. Consent for the Westport works is unlikely to be granted while that remains unaddressed, so Carters Beach is pivotal to the wider scheme progressing. Carters Beach protection is costed at about $6.5 million, of which about $2.8 million of co-funding has been identified, meaning Westport ratepayers will be asked to underwrite up to $3.7m.
Snodgrass Road is not being left out. The West Coast Regional Council is committed to providing flood protection for Snodgrass Road and the plan is that it will be delivered at a later date. It is not part of this consultation because nothing about it has changed and it carries no new rates proposition. It will be consulted on with the community in the future.
Will there be community information evenings to explain the Project reset and proposed consultation further?
We are planning on holding two community information meetings with the dates to be confirmed. One will be held at Carters Beach Hall and one at NBS Westport.
More will be held if required.
Where can I find out more?
You can attend one of our community drop-in sessions on Wednesdays between 11am and 1pm at 147 Palmerston Street, Westport.
Closer to the consultation start date, more information will also be available on the West Coast Regional Council website: www.wcrc.govt.nz/community/consultation
What is the process once the Special Consultative Procedure is complete?
The results of the consultation will be analysed in October and collated into a report for the West Coast Regional Council.
Public hearings for those who to speak to their submissions will be held on 27 October 2026 (11am-3pm approx). They will be held in Westport.
The results of the Special Consultative Procedure will be placed before the full West Coast Regional Council at its 1 December 2026 meeting.
Your Questions Answered
-
What other option was considered?
Another option was considered in detail but has been set aside based on affordability. This option involved the main flood scheme and Carters Beach being built to the same 1.5% AEP (Annual Exceedance Probability) protection level as Option One and Option Two, but with additional stopbank height to address forecast changes in climate over the next 30 years.
This option would involve stopbanks approximately 0.3 metres higher than the other options but because it cost about $8.8m more than Option One and $7.7m more than Option Two, it was considered too high an additional cost for the community to meet and was set aside as an Other Option considered.
-
The original scheme proposed to provide 1 in 100-year level of flood protection.
The level of freeboard (extra height allowance for uncertainty) was 600mm but this has been reduced due to enhanced computer modelling.
This scheme would now cost around $70m to deliver.
RCP6 was factored into the original design.
-
ARI stands for annual recurrence interval which is sometimes also known as ‘return period’. It is the average time period between floods of a certain size. For example, a 50 year ARI event would on average happen every 50 years.
-
AEP stands for annual exceedance probability (AEP) which is the probability of an event occurring in any given year.
So a 1% AEP means there is a 1% chance in of the event occurring in any given year of the event occurring. This means that on average 1 event of this size will occur every 100 years. Therefore, 1% AEP is equal to a 100 year ARI, a 2% AEP is a 50 year ARI, and a 10% AEP is a 10 year ARI. Both ARI and AEP values are based on statistical calculations and represent the average timing of events.
-
RCP stands for Representative Concentration Pathways (RCP). These are climate change scenarios to project future greenhouse gas concentrations.
These pathways (or trajectories) describe future greenhouse gas concentrations (not emissions) and have been formally adopted by the Intergovernmental Panel on Climate Change (IPCC).
The pathways describe different climate change scenarios, all of which were considered possible depending on the amount of greenhouse gases (GHG) emitted in the years to come.
-
RCP 4.5 is described by IPCC as a moderate scenario in which emissions peak around 2040 and then decline. RCP 8.5 is the highest baseline emissions scenario (essentially business as usual) in which emissions continue to rise throughout the twenty-first century. In the Westport context, RCP 6 is applied in terms of climate modelling, which reflects some stabilisation of climate emissions. This is based on NIWA advice.
-
Freeboard is additional stopbank height to address uncertainties. It is extra height built on top of the design flood level as a safety margin.
It is usually measured in millimetres and the higher the level of freeboard the greater contingency for ‘over design’ events (events that exceed the design flood level).
The original Westport scheme included a freeboard provision of 600mm. That will now be 400mm.
The technical definition of freeboard is presented in Section 1.2.2 Definitions of New Zealand Standard NZS 4404:2010 Land Development and Subdivision Infrastructure. That states:
A provision for flood level design estimate imprecision, construction tolerance, and natural phenomenon (such as waves, debris, aggradations, channel transition, and bend effects) not explicitly in the calculations.
-
The structural make-up of the floodwalls will be shared when the final design is complete. The current plan for the whole flood mitigation project involves a combination of earth stopbanks, ‘planter-box’ stopbanks, concrete floodwalls, wooden floodwalls, and portable flood barriers.
-
Westport's stormwater and wastewater network, like those in many towns and cities throughout New Zealand, suffers from aging and under-invested infrastructure. Significant upgrades may be required to ensure functionality and resilience in the future.
Westport’s small population and rating base is a significant challenge for further network improvements and work is widely dependant on external funding.
Buller District Council (BDC) is working on ways to improve this and integrate improvements with the planned new floodwalls.
BDC is currently completing stormwater network modelling, which together with an improved understanding of the current stormwater infrastructure will help identify the scope of work required. The integrated stormwater will provide a range of design options and costings, including affordability considerations. The concept study will be completed mid-August 2024, which will then guide and inform next steps, including application for further government funding support due to the affordability challenges.
Alongside stormwater network upgrades another key long-term objective is network separation (separating stormwater from wastewater) and wastewater modelling to establish how to optimise the performance of the stormwater and wastewater systems.
A report by Worley's presented to Council in late 2024 provides options for creating a flexible and cost-effective stormwater management system to reduce flooding in Westport during both routine and extreme weather events. This includes using high-capacity and mobile pumps, as well as nature based solutions such as rain gardens and detention basins.
Further modelling is required before decisions can be made about actioning the suggestions made in the report. A Regional Infrastructure Fund applicaiton has been made meanwhile to secure possible funding.
Buller Flood Recovery and subsequent work
Efforts to improve the stormwater system have been undertaken in the immediate wake of the floods.
As part of the post-flood essential infrastructure repairs, National Emergency Management Agency (NEMA) funded the lifting of four wastewater pumpstation electrical cabinets to above 1 in 100 year flood height. These were: North Beach pumpstation, Derby Street pumpstation, Rintoul Street and Roebuck Street pumpstation.
It is hoped that more pumpstations can be lifted in the future. This work will be prioritised based on flood risk and in conjunction with long term pumpstation renewal schedules.
Nineteen WaStop® valves have also been installed at key stormwater outfalls throughout the Westport township. The valves provide more network resilience and are better able to protect against floodwater infiltration (backflow) at many key stormwater outfalls.
Crown Infrastructure partners Better Off funding covered the cost of supplying and installing 14 of these WaStop® devices. Another 5 were installed with funding from National Emergency Management Agency (NEMA) as part of the post-flood essential infrastructure repairs.
-
The wave buoy located off the coast of Westport will be used to collect data in real time, including maximums, means and minimums for wave period, height and direction; wind speed and direction; sea temperature, and barometric pressure.
This information, collected over time, will form a valuable dataset able to be used to update the flood model that the National Institute of Water and Atmospheric Research (NIWA) has developed for Westport, in partnership with the WCRC.
These datasets will also help those developing the flood models to set more appropriate downstream boundary conditions for the flood inundation maps that are created from the flood model forecasts.
Unfortunately, the wave buoy was badly damaged in a storm in 2024 when it came free of its mooring, and it’s hoped a replacement will be in place in early 2025.
You may ALSO be interested in:
Media Release: Regional councillors unanimously agree to the next steps for Westport Flood Protection Scheme reset
Media Release: Regional Councillors to consider next steps for Westport flood protection scheme
Media Release: Drill rig to be spotted around Westport
Media Release: Work on McKenna stopbank wraps up
Media Release: Ceremony to mark the breaking of ground on Mckenna stopbank
Media Release: Work to start on Floating Lagoon vegetation clearance
Media Release: Start of Cats Creek work marks important milestone

