Westport Flood Protection Scheme

Reset

Kawatiri Coastal Trail - Carter's Beach Westport

In 2026, a review of the Westport Flood Protection Scheme (WFPS) has been carried out, after it became clear that there were affordabilty issues.

The costs of the original scheme are now predicted to reach about $70 million, so the project team has worked on ways to reduce that and still deliver a more credible scheme.

One tool for doing so is to lower the level of protection to Westport to protect against an approximately 1 in 67-year flood (similar to July 2021) – as opposed to 1 in 100-year previously proposed. The level of freeboard (extra height allowance for uncertainty) would also be reduced from 600mm to 400mm following enhanced computer modelling.

The project reset has financial implications for ratepayers and represents additional debt for West Coast Regional Council (WCRC).

These proposed changes represent a significant variation from what is included in the West Coast Regional Council’s current Long-Term Plan (2024-2034) and what was consulted on with the community in 2021. Therefore, additional consultation is required using a Special Consultative Procedure.‍ ‍

Special Consultative Procedure

A Special Consultative Procedure (SCP) is a highly structured, formal public consultation process governed by the New Zealand Local Government Act 2002

On 25 August 2026, Regional Councillors approved Council undertaking a Special Consultative Procedure on proposed scheme changes and voted to approve the next set of actions to progress the reset of the scheme.

The Special Consultative Procedure will ask the community to consider two options (below). Another option was considered but deemed too costly.

Option One is the main Westport Flood Protection Scheme (the Core Protection Scheme) built to a 1.5% AEP (Annual Exceedance Probability) protection level, based on the current climate, with 400mm of freeboard (extra contingency height). Plus, the revised alignment of the Carters Beach stopbank built to a 1.5% AEP, and 300mm of freeboard. This level of protection would protect Westport from a comparable flood to the July 2021 event but does not allow for future climate change.

Option Two is an Optimised Hybrid Scheme that builds on Option One for Westport and Carters Beach. It is designed for current climate conditions, with allowance to raise the height of the floodbanks in the future. The additional cost is estimated at about $1 million. The difference is that at select constrained locations, short sections of stopbank would be constructed with a wider footprint that can be cost-effectively built on in the future. For now, they would be built to the same height as Option One and offer the same level of flood protection.

Dates for the consultation will be advertised once finalised. The next step is for the WCRC to consider and approve the consultation at its 1 September 2026 meeting.

Cost implications

The tables below indicate the costings and rating implications of the proposed options:

Option One

Option Two

What is the plan for Carters Beach and Snodgrass Road?

It is still the intention to deliver flood protection for these communities. 

Flood protection at these locations was not funded by central government, despite Carters Beach being including in the Kawatiri Business Case request for co-funding.  

This Special Consultative Procedure includes funding for Carters Beach, as it has interdependencies with the main scheme and must be delivered alongside it. 

The flood modelling shows that building the Westport stopbanks will change how water moves in the Lower Buller, affecting Carters Beach. Consent for the Westport works is unlikely to be granted while that remains unaddressed, so Carters Beach is pivotal to the wider scheme progressing. Carters Beach protection is costed at about $6.5 million, of which about $2.8 million of co-funding has been identified, meaning Westport ratepayers will be asked to underwrite up to $3.7m. 

Snodgrass Road is not being left out. The West Coast Regional Council is committed to providing flood protection for Snodgrass Road and the plan is that it will be delivered at a later date. It is not part of this consultation because nothing about it has changed and it carries no new rates proposition. It will be consulted on with the community in the future.

Will there be community information evenings to explain the Project reset and proposed consultation further?

We are planning on holding two community information meetings with the dates to be confirmed. One will be held at Carters Beach Hall and one at NBS Westport.   

More will be held if required.

Where can I find out more?

 You can attend one of our community drop-in sessions on Wednesdays between 11am and 1pm at 147 Palmerston Street, Westport.  

Closer to the consultation start date, more information will also be available on the West Coast Regional Council website:  www.wcrc.govt.nz/community/consultation

What is the process once the Special Consultative Procedure is complete?

The results of the consultation will be analysed in October and collated into a report for the West Coast Regional Council. 

Public hearings for those who to speak to their submissions will be held on 27 October 2026 (11am-3pm approx). They will be held in Westport. 

The results of the Special Consultative Procedure will be placed before the full West Coast Regional Council at its 1 December 2026 meeting.

Your Questions Answered