Lower orowaiti

Kawatiri Coastal Trail - Carter's Beach Westport

The scheme is divided into five main sections of stopbanks:

Lower Orowaiti, Upper Orowaiti, North End, Lower Buller (Wharf to Buller Bridge) and Upper Buller (SH67 from Buller Bridge to Nine Mile Road).

Lower Orowaiti covers the area in Westport between Craddock Drive and Eastons Road to where it meets Stephen Road.

The stopbanks planned for there aim to protect homes from overflow from the Orowaiti River and estuary.

This section is made up of:

  • Avery’s stopbank

  • Eastons Road SH67 to Stephen Road

  • and Craddock Drive to Avery’s stopbank.

Avery’s stopbank

The Avery’s stopbank is part of the Lower Orowaiti section.

  • The consent application for Avery’s stopbank was lodged in late June. Consenting is expected to take 6 to 8 weeks.

  • The geotechnical work is complete for Avery’s, along with final design.

  • Rosco Contracting Ltd has been awarded the tender to construct the stopbank and install the culverts, being supplied by Humes.

  • A major culvert requires replacing as part of the work, as well as some smaller culverts. Culvert pipes have been pre-purchased. The team has worked closely with Buller District Council over this part of the process.

  • Construction is scheduled to commence in August/September, following consenting.

  • When construction gets underway, it is expected to involve temporary road closures on Orowaiti Road to allow for safe installation of the culvert and construction of the stopbank. Traffic management plans will be in place and communicated in advance to minimise disruption.

  • Construction on Avery’s stopbank is expected to take about four months.  

  • The anticipated height of this stopbank would be between 1.1 and 1.5 metres high – up to 1.7 metres as it travels over the culvert. It will be between 15 and 20 metres wide at the base.

  • Engagement with affected homeowners is being carried out as part of the pre-consent work.  

  • The stopbank is about 540-metres long.

  • In August 2025, some trees are being removed along Orowaiti Road to prepare the space for the stopbank once construction gets underway.

What about the balance of the Lower Orowaiti section?

Geotechnical investigations are underway at Eastons Road SH67 to Stephen Road, and Craddock Drive to Avery’s stopbank. Provisional design is underway, but assessing the condition of the land is a key element of detailed design.