Frequently Asked Questions-

Westport Flood Protection Scheme

Frequently Asked Questions (FAQs)

August 2026

‍ ‍‍Westport Flood Protection Scheme reset

‍ ‍Special Consultative Procedure Frequently Asked Questions (FAQs) as at August 2026

‍ Note, the FAQs below are a sample of the full document that can be downloaded here.

‍‍What is the Westport Flood Protection Scheme?

‍ The Westport Flood Protection Scheme (WFPS) is a combination of structures such as earth stopbanks, ‘planter-box’ floodwalls, concrete floodwalls, and portable flood barriers around Westport that are designed to reduce the impact of flooding associated with the Buller and Orowaiti rivers. The total length of the main protection scheme for Westport is over 16km.

‍ ‍The WFPS is being delivered by the West Coast Regional Council and is part funded by the government via the Resilient Westport programme of work.

What is a Special Consultative Procedure?

‍ A Special Consultative Procedure (SCP) is a highly structured, formal public consultation process governed by Section 83 of the New Zealand Local Government Act 2002.

‍ ‍The West Coast Regional Council is legally required to trigger an SCP under specific conditions outlined in their Long-term Plan and legislation. In this case, the changes proposed represent an amendment to Council’s current Long-Term Plan (LTP) 2024-2034.

‍ ‍Why do a Special Consultative Procedure?

‍ ‍The WFPS needs to be revised and reset to deliver a more affordable solution, that still achieves a significant reduction in the flood hazard. This means considering: ‍ ‍

  • The impact on rates arising from the increased cost of the scheme 

  • Changes to the level of flood protection to be delivered for Westport  ‍

  • Funding flood protection for Carters Beach. 

‍ ‍These proposed changes represent a significant variation from what was included in the West Coast Regional Council’s Long-Term Plan (2024-2034) and what was consulted on with the community in 2021. Therefore, additional consultation is required.

‍ ‍A Special Consultative Procedure is triggered under the West Coast Regional Council’s Significance and Engagement Policy.

Consultation is planned for September 2026 – exact dates to be confirmed.

‍ ‍Will there be community information evenings to explain the Project reset and proposed consultation further?

‍ We are planning on holding two community information meetings with the dates to be confirmed

‍ ‍More meetings will be held, subject to demand.

‍ ‍Where can I find out more?

‍ ‍Go to the Resilient Westport website (under Flood Protection/Special Consultative Procedure). 

‍ ‍Closer to the consultation start date, more information will also be available on the West Coast Regional Council website:  www.wcrc.govt.nz/community/consultation

‍ ‍You can also attend one of our community drop-in sessions on Wednesdays between 11am and 1pm at 147 Palmerston Street, Westport. 

What is the process once the Special Consultative Procedure is complete?

‍ The results of the consultation (expected in September/October) will be analysed in October and collated into a report for the West Coast Regional Council. 

‍ Public hearings for those who wish to speak to their submissions will be held on 27 October 2026 (11am-3pm approx). They will be held in Westport. 

‍ The results of the Special Consultative Procedure will be placed before the full West Coast Regional Council at its 1 December 2026 meeting.

What is the plan for Carters Beach and Snodgrass Road?

‍ It is WCRC’s intention to deliver flood protection for these communities.

‍ Flood protection at these locations was not funded by central government, despite Carters Beach being including in the Kawatiri Business Case request for co-funding.

This Special Consultative Procedure includes funding for Carters Beach, as it has interdependencies with the main scheme and must be delivered alongside it.

‍ The flood modelling shows that building the Westport stopbanks will change how water moves in the Lower Buller, affecting Carters Beach. Consent for the Westport works is unlikely to be granted while that remains unaddressed, so Carters Beach is pivotal to the wider scheme progressing. Carters Beach protection is costed at about $6.5 million, of which about $2.8 million of co-funding has been identified, meaning Westport ratepayers will be asked to underwrite up to $3.7m.

‍ Snodgrass Road is not being left out. The West Coast Regional Council is committed to providing flood protection for Snodgrass Road and the plan is that it will be delivered at a later date. It is not part of this consultation because nothing about it has changed and it carries no new rates proposition. It will be consulted on with the community in the future.

What are the Options being consulted on?

‍ ‍Option One

  • ‍ ‍The main Westport Flood Protection Scheme (the Core Protection Scheme) would be built to a 1.5% AEP (Annual Exceedance Probability) protection level, based on the current climate, with 400mm of freeboard (extra height allowance for uncertainty) and the revised alignment of the Carters Beach stopbank built to a 1.5% AEP, plus 300mm of freeboard level of protection.

  • ‍ ‍This level of protection would protect Westport from a flood comparable to the July 2021 event but does not allow for future climate change.

  • ‍ ‍The additional funding required for the Core Protection Scheme (Option One) is $22.5 million. This is in addition to the $10.2 million already committed via rates and consulted on in 2021.

  • ‍This includes $3.7 million for flood protection for Carters Beach.

‍ ‍Option Two

‍ ‍ Option Two (the Optimised Hybrid Scheme) builds on Option One for Westport and Carters Beach. It is designed for current climate conditions with the ability to raise stopbanks in the future.

  • ‍ ‍The additional cost is estimated at about $1.1 million.

  • ‍ ‍ The difference is that at selected locations, short sections of stopbank would be constructed with a wider base footprint while retaining the same crest height as Option One. This would mean that if the stopbanks were to be raised in the future, then the base foundation would already be in place.

  • ‍ ‍This is a targeted adaptation measure. It makes it easier to raise the stopbank height in the future in the places where it would otherwise be difficult and costly. The rest of the alignment can be raised as required.

  • ‍ ‍This option requires approximately 10% more structural fill than the Core Protection Scheme (Option one). In return, rock protection, filter layers, geotextile and toe works can be positioned on the future alignment now.

  • ‍ The level of flood protection in the meantime is the same as Option one i.e built to a 1.5% AEP protection level, based on the current climate, with 400mm of freeboard. It would protect Westport from a comparable flood to the July 2021 event but allows for works to top up the stopbanks in the future, to help manage climate change.

  • ‍ ‍The additional funding required for Option Two is $23.60 million. This is in addition to the $10.2 million already committed via rates and consulted on in 2021.

  • ‍ ‍This includes $3.7 million for flood protection for Carters Beach.

‍ ‍Why has the cost changed so much?

‍ The scheme that was applied for in 2021 and 2022 is very different from the scheme that is now being designed and priced. The early figures came from concept work. A possible alignment had been drawn at a high level, earthwork volumes were estimated from a single point along the proposed alignment, a flat allowance was added for unknowns, and ground investigation, consenting, and risk allowances were not included, but are real-world delivery costs.

‍ The updated scheme costs come from more detailed cost estimates using a peer-reviewed preliminary design off three-dimensional models. Setting the two side by side, this is more than just a price increase.

‍ ‍Five things changed in the scheme itself as the design work was done:

The stopbanks had to get bigger. Geotechnical work and engineering review required flatter, more stable sides, requiring a large increase in stopbank material.

Seepage control had to be added. An independent review found that water moving underneath and through the banks in a flood (seepage) had not been allowed for. The concept design never contemplated this, and seepage control is now the single largest driver of both cost and remaining risk.

The scheme had to get longer. Detailed flood modelling showed protection had to extend about 700 metres further up the Buller River, alignments shifted in places, and extra work was needed in a number of places. A flood protection system works in an integrated manner, so these were not optional.

The materials changed. Locally won river gravel was proposed for stopbank material but is not adequate to prevent seepage, so more engineered (and costly) material is required.

The real costs of delivery came in. Consenting, land access, ground investigation, independent reviews, safety in design, and a measured allowance for risk are all costed now with greater accuracy. These costs weren’t included in initial estimates yet are real delivery costs.

Our funding situation in a nutshell:

‍ Central Government has committed $15.6 million to physical flood protection for Westport. The 2021 consultation resulted in the West Coast Regional Council committing $10.2 million to the scheme – totalling around $26 million in funding for the main scheme (excluding Carters Beach and Snodgrass Road).

‍ The figures being consulted on include Carters Beach as it is considered integral to the scheme but was not granted funding from Central Government.

‍ The project team is advocating for additional government funding and has a Regional Infrastructure Fund (RIF) application pending.

‍ There is a pledge from several local businesses of around $1.8 million, which is intended to be initially directed to structural works at Carters Beach due to the level of urgency. The WCRC is committed to delivering flood protection for Snodgrass Road in the future.

What has been the process to arrive at these costs?

‍ The engineers, project manager, and other experts have worked extensively on a revised scheme. They have come up with scenarios to deliver a more affordable scheme, without compromising safety or integrity and still protecting Westport from a similar event such as the July 2021 flooEach scenario required an examination of the level of flood protection, revised hydraulic modelling to assess flood impacts with and without the proposed scheme and also its performance in large flood events, stopbank alignment, technical solutions (seepage, ground conditions, material) and sequencing (maximising the timing of work for efficiency).

What about maintenance and ongoing costs?

‍ WCRC will maintain the stopbanks and the cost will be included in rates. In 2027, that would be $11.72 annually (based on a property valued at $369,000), going up to $14.91 by 2034.

How long could the scheme take to build?

‍ The revised scheme plans to see completion of construction of the main flood protection scheme and Carters Beach by the end of 2029.  

‍ Flood protection projects of comparable scale and size can realistically take 5 to 10 years to complete. The planning and investigative work we have done to date is extensive so we think we can deliver the balance of the work in next three years.

What are the design and construction challenges?

‍ Our investigations have confirmed that many sections of the flood scheme face technical and constructability challenges, including seepage, stability, constrained corridors (narrow areas near homes or roads), utilities and contaminated land.

‍We are committed to resolving these issues because of their importance. Key decisions are still being worked through on matters such as seepage treatment, floodwall types and fill sources, because these have material implications for affordability and buildability.

What other option was considered?

‍ Another option was considered in detail but has been set aside based on affordability. This option involved the main flood scheme and Carters Beach being built to the same 1.5% AEP (Annual Exceedance Probability) protection level as Option One and Option Two, but with additional stopbank height to address forecast changes in climate over the next 30 years.

‍ This option would involve stopbanks approximately 0.3 metres higher than the other options but because it cost about $8.8m more than Option One and $7.7m more than Option Two, it was considered too high an additional cost for the community to meet and was set aside as an Other Option considered.

When did the project team get started?

‍ While floods that gave rise to the Flood Protection project occurred in 2021 and 2022, it took several years for the project to be established and secure funding. Therefore, the project has effectively been operating for around 2 and a half years (since early 2024).

What was the project establishment timeline?

‍ After the floods of 2021 and 2022, a business case was put to government to co-fund flood resilience for Westport.

‍ In May 2023, government announced a $22.9 million funding package (Resilient Westport). In September 2023, the Department of Internal Affairs approved the $15.6 million funding for flood protection.

‍ A technical review of the structural concept for the scheme, commissioned by the Department of Internal Affairs, was carried out between November 2023 and February 2024. Concerns raised there were addressed and/or mitigated.

What Resource Consent Applications are pending?

‍ There are Resource Consent applications lodged with consenting authorities for the Floating Lagoon stopbank, as well as a joint application for Carters Beach and Upper Buller. We continue to work with the consenting authorities to facilitate those consents. Those consents have been on hold in recent times whilst we seek the mandate of the community and local governance to continue the scheme under new settings. Once we have the two options to consult on, these will be progressed with the consenting authorities.‍ ‍

Technical terms

What is seepage?

‍ Seepage is the slow escape of water through or under a stopbank during high river levels. While minor, controlled seepage helps relieve internal water pressure, excessive or uncontrolled seepage creates internal erosion, piping, and structural instability that can lead to the collapse of the flood defence.

What is crest level?

‍ Crest level is the designed height of a stopbank’s flat top. This can vary in width according to the dimensions of the stopbank.

What is batter?

‍Batter in a stopbank refers to the angle of the slope along the sides. It stablilises the earthen wall. A stopbank with a 2:1 ratio is steeper than a 3:1 slope, which are easier to maintain and carry less of a slumping risk. The new design proposes using 3:1 batters where possible.

What is the toe?

The toe of a stopbank is the bottom edge where it meets the ground.

What is level of service?

Level of service relates to the way flood protection works are designed and constructed and can include the height of the flood you are protecting against, future climate provisioning (how much extra height we build into the scheme to allow for future climate change), and freeboard (additional stopbank height to address uncertainties).

What does ARI mean?

ARI stands for annual recurrence interval (ARI) which is sometimes also known as ‘return period’. It is the average time period between floods of a certain size. For example, a 50-year ARI event would on average happen every 50 years. 

What does AEP mean?

AEP stands for annual exceedance probability (AEP) which is the probability of an event occurring in any given year. 

So a 1% AEP means there is a 1% chance in of the event occurring in any given year of the event occurring. This means that on average 1 event of this size will occur every 100 years. 

Therefore, 1% AEP is equal to a 100-year annual recurrence interval, a 2% AEP is a 50-year ARI, and a 10% AEP is a 10-year ARI.  

What annual recurrence interval does a 1.5% AEP have?

A 1.5% AEP has a 1-in-67 chance of a specific flood or rainfall event occurring or being exceeded in any given year.

What is freeboard?

Freeboard is additional stopbank height to address uncertainties. It is extra height built on top of the design flood level as a safety margin.

It is usually measured in millimetres and the higher the level of freeboard the greater contingency for ‘over design’ events (events that exceed the design flood level). 

The original Westport scheme included a freeboard provision of 600mm. That will now be 400mm. The lower level is supported by improved computer modelling.

What is a 30-year climate provision?

A 30-year climate provision generally refers to planning at least 30 years into the future to identify, manage, and reduce community and infrastructure risks from climate-related natural hazards, such as extreme weather events and sea level rise. 

What does RCP mean?

RCP stands for Representative Concentration Pathways (RCP). These are climate change scenarios to project future greenhouse gas concentrations. RCP6 reflects a scenario where emissions continue to rise but there is some stabilisation by 2100. RCP6 was factored into the original design.‍ ‍‍

Option One

Option Two