An agreement has been reached with the Ministry for Cities, Environment, Regions and Transport (MCERT) and the Westport Flood Protection Scheme team to extend the timeframe for the current Central Government funding for the scheme.
MCERT and National Infrastructure Funding and Financing (NIFF), which acts as monitor and administers the funding on MCERT’S behalf, have been engaged in discussions with the West Coast Regional Council and project team on extending the funding window for the government’s remaining contribution to the scheme.
That agreement has now been reached in principle and will see funding released based on agreed milestones and gateways to deliver the project. A variation to the MCERT Funding Agreement is being finalised.
In a letter sent to the West Coast Regional Council in November, MCERT recognised the constructive way the council had worked with NIFF on the reset and signalled it looks forward to working with the Regional Council to progress “this important project for Westport”.
West Coast Regional Council Capital Programme Manager Tom Hopkins says it is great for the scheme to have more certainty over the funding pathway and to have reached agreement on a way forward.
“It also means that Regional Councillors will have this information when they consider next steps for the project at their 1 December meeting, next week.”
The Westport Rating District Joint Committee will be updated this week on project status.
Physical flood protection works are targeted for completion by December 2029, subject to future decisions, funding and approvals.
[ends]